An 80% complete build, verified room by room.

This immersive dossier shows what Sterling clients receive: on-site evidence, structured findings, and practical next steps before more capital moves.

Sample villa · Residential build~80% reported completionHold next tranche pending review

Scroll to walk the sample report

Station 01 · Structure

Structure matches the approved plan.

Block work, slab continuity, and roof frame alignment were checked against the latest architectural set and contractor claims.

Verified on site · 14 May
  • Block courses and openings align with plan grid
  • Roof frame installed; no visible structural drift
  • Contractor progress photos match live conditions

Station 02 · Envelope

Roofing and weatherproofing are underway, not complete.

Sterling confirmed installed roof sheets, flashing gaps, and areas still exposed to weather before the next payment tranche.

Partial completion · flagged
  • Primary roof pitch installed on main block
  • Secondary block still un-sheeted
  • Drainage falls not yet verified after recent rains

Station 03 · Finishes

Interior finishes are behind the schedule presented to the client.

Plaster, electrical first-fix, and joinery readiness were compared to the contractor timeline shared with the investor.

Behind schedule · medium risk
  • Plaster incomplete in two bedrooms
  • Electrical conduits visible; fittings not installed
  • Client was told 'ready for paint'. Not observed

Station 04 · Exterior context

Drone and perimeter evidence confirm overall site status.

Aerial capture validated access routes, material storage, and visible completion relative to neighbouring plots.

Evidence package attached
  • Drone orbit confirms roof coverage gap
  • Material stock consistent with active work, not hoarding
  • Perimeter security adequate for current stage

After the walkthrough

What Sterling adds once the site work is done.

The site visit is only the first layer. You also receive a dedicated oversight agent, structured financial review, risk flags, and a clear recommendation before you release more funds.

Assigned to you

Your Sterling oversight agent

Pacifier Duve

Dedicated oversight agent

Pacifier Duve will be your assigned Sterling agent, monitoring your project from A to Z. No more guessing from a distance. Site progress, invoice review, and clear updates reach you before small issues turn into expensive problems. That is the reassurance most remote builds rarely give. Terms and Conditions apply.

  • Owns oversight from briefing through project completion
  • Runs site verification, invoice review, and milestone follow-through
  • Executes project-relevant errands you assign within agreed scope
Schedule a call

Invoice review

Each line is compared to the agreed quote or scope. The status column explains what Sterling found.

Sample table

Status key

  • Over quoteThe bill is higher than the agreed quote.
  • Matches quoteThe invoice aligns with what was quoted.
  • Outside scopeA new charge that was not in the original scope.
  • Above agreed termsPayment terms exceed what was previously agreed.
Line itemQuotedBilledFinding
Roofing bundle$18,400$22,100Over quoteBill exceeds quote by $3,700
Steel reinforcement$9,800$9,650Matches quoteWithin agreed amount
Plaster & skimNot in scope$3,200Outside scopeNew charge not in original agreement
Labour advance10%25% requestedAbove agreed termsAdvance exceeds agreed percentage

Risk flags

  • high
    Completion misrepresentation

    Contractor claimed ~95% completion; Sterling observed ~80% by scope.

  • medium
    Weather exposure

    Partial roof install leaves interior areas exposed ahead of plaster completion.

  • low
    Material presence

    On-site stock supports active work, but not the full pending invoice.

Sterling recommendation

Do not release the next tranche until roof completion and a revised schedule are documented. Request itemised invoice support for steel and roofing bundles before approval.

  • Hold pending tranche until roof closure is verified
  • Require revised milestone schedule with finish dates
  • Schedule follow-up visit within 21 days